What aspects should be paid attention to in the installation verification of the copper bars of the wind turbine inverter?
2026-04-09
The core of the installation verification after the copper bars of the wind turbine inverter are installed is to focus on three things: no heating, no sparking, no loosening, and sufficient insulation. Below, I will list them for you in the order of the items that can be directly executed on-site, with clear priorities and no omissions.
1
Appearance and mechanical installation inspection
Copper bar direction and spacing
- The positive and negative poles, as well as the AC and DC copper bars, should be arranged neatly, without sharp corners or bends, and without obvious stress pulling.
- The electrical clearance between phases / ground and the creepage distance should meet the voltage level (generally, for AC 690V, the clearance is ≥14mm, for DC 1000V, it is ≥20mm, according to the overall machine specifications).
- There should be no interference or friction points between the copper bars, the copper bar and the housing, and the copper bar and the wiring harness.
Supporting and fixing
- The number and position of the supporting insulators should be correct, and there should be no long sections of suspension (to prevent short circuits, electrical force deformation).
- All necessary fasteners should be complete: spring washers / flat washers / anti-loosening parts should be complete, with no missing or incorrect installation.
- The copper bar should have no obvious warping or force deformation.
2
Connection and contact surface verification (the most critical, the area with severe heating)
Contact surface matching
- The bonding surface should be completely adhered, without 翘边, without gaps, and without foreign substances (dust, burrs, insulation debris).
- The bonding length should be sufficient, without unilateral force, eccentric compression.
Lag bolt verification
- It must be tightened using a torque wrench according to the process value, and it is strictly prohibited to rely on hand feel.
- Check if the bolt sealing / anti-loosening marks are consistent, and there should be no missed or incorrect tightening.
- For multi-bolt connections, tighten them in a diagonal manner in stages to avoid local warping.
Coating and protection
- The contact surface should be free of oxidation, dirt, and scratches.
- The conductive paste / anti-oxidant should be applied evenly, without overflowing and contaminating the insulation parts.
3
Electrical performance testing
Contact resistance test (must be done)
- Use a micro-ohmmeter / loop resistance tester to measure the resistance of the bonding points.
- The qualified standard is: for single bolt connection points, it should be ≤50μΩ, and for large current copper bars, it should be ≤20~30μΩ.
- If the resistance of the same specification connection points is too large, it indicates poor contact.
Insulation resistance test
- Measure the insulation of the DC and AC circuits to the casing and between each other.
- Under normal temperature, the general requirement is ≥100MΩ (variations in different manufacturers' standards are slight).
- Check for insulation weaknesses caused by copper bar corners, burrs, and metal debris.
Withstand voltage test (Hi-pot)
- Apply AC/DC withstand voltage according to the overall machine specifications. The copper bar should have no flashover or breakdown.
- Pay special attention to the copper bar corners, support seats, and the intersection position of the wiring harness.